Link materials in Production Control to a prepurchased ABM (advanced bill of materials) by using the Link
Job command. Tekla
PowerFab uses reference numbers to match the materials across
modules. Any unlinked materials, such as loose pieces, will be loaded into a requisition or
a purchase order to be purchased.
-
In the
Select Production Control Job dialog, open a job and click the Production Control ribbon tab.
-
On the menu, select .
The Link
Filters dialog opens.
-
To limit which materials are
linked, do the following (Optional):
-
Select a filter type in
the Type list, and click Select.
-
Click the arrow buttons
to move the items that you want to link to the Included list.
-
Click
OK.
You return to the
Link
Filters dialog.
-
Select the If updating a cut list item,
exclude from being cut checkbox. (Optional)
By selecting the checkbox, you
can ensure that Tekla
PowerFab does not invalidate the entire
cut list when an item in the cut list is updated. Updated items will be
saved in the inventory to be processed later.
-
Click Link.
The Link
Items dialog opens.
-
Click Requisitions if you want to load material information to a requisition or Purchase Orders if you want to load material information to a purchase order.
-
Click the desired requisition or purchase order.
-
Click
OK to load the materials.
-
Click
OK to close the Link
Items dialog.