Finalize a production control job

Tekla PowerFab
Modified: 18 Nov 2024
2025
Tekla PowerFab

Finalize a production control job

You can prevent any further changes to a production control job by using the Finalize command. After finalizing the production control job, you can no longer send material to purchasing.

The requisitioned items assigned to the job will be deleted, and inventory items reserved for the job will be unreserved.

Note: Finalizing a job is irreversible and cannot be undone.
  1. In the Select Production Control Job dialog, open a job and click the Production Control ribbon tab.
  2. On the menu, select Purchasing > Finalize.
  3. If you are sure that you want to finalize the job, inthe Finalize Job dialog, click Finalize.
Was this helpful?