Adjust labor times for copes, punches, and stiffeners

Tekla PowerFab
Modified: 10 Mar 2026
2026
Tekla PowerFab Tekla PowerFab GO

Adjust labor times for copes, punches, and stiffeners

You can adjust the default labor times for the layout of copes, punches, and stiffeners. For stiffeners, you can also adjust the fit-up time. The labor times that you define will be used in all estimating jobs.

Users with administrator rights need to grant the relevant access rights for other users on the Estimating Labor tab in File > Administration. See Manage user permissions.

  1. Click the Maintenance ribbon tab.
  2. On the menu, select Estimating > Labor Maintenance > Cope / Punch / Stiffeners.

    The Cope Punch Stiffener dialog opens.

  3. Type labor times for the different copes, punches, and stiffeners.
  4. Click Save.