Combine items in the Requisition # dialog box

Tekla PowerFab
修改时间: 8 3月 2024
2024i
Tekla PowerFab Tekla PowerFab GO

Combine items in the Requisition # dialog box

You can mult and nest requisition items using the Combine command. Combining requisition items creates a list of materials that you can later send out for pricing.

  1. On the Requisitions tab in the Select Requisition/Purchase Order dialog box, open a requisition.
  2. Click the Requisition ribbon tab and select Combine.

    The Select Combining Run dialog opens. When you are performing the first combining run for a combining job, the list in the dialog is empty.

  3. Click a desired combining option to select it.

    The options are:

    • Mult: Combines linear items, like beams and angles.
    • Nest: Combines items that have area, like plates or gratings.
    • Mult & Nest: Combines all items.

    The Combining Run Filters dialog opens.

  4. To only combine specific types of materials do the following (Optional):
    1. Select a filter type in the Type list and click Select.
      The Filter dialog opens.
    2. Do one of the following depending on the filter type:
      • Click the arrow buttons to move the items that you want to combine to the Included list.
      • Type the maximum and minimum values for the items that you want to combine.
    3. Click OK to apply the filter.

      You return to the Combining Run Filters dialog.

  5. To ensure that you are using the correct settings, click the Optimizations, INV Filter, and Suppliers buttons.

    You can modify the settings.

  6. To combine the materials, click the button at the bottom of the Combining Run Filters dialog, or press F4.

Tekla PowerFab combines the materials. After the combining process is finished, the Combining Run Results dialog opens.

(1) Navigation tree: Result statuses

  • Combined: The items have been optimized successfully
  • Not Combined: The items that failed to be optimized
  • Exception: Items that cannot be optimized, such as comment and buyout lines. These can generally be ignored

(2) Display area: Combining results including each bar or sheet that is required

(3) Bottom area: The items that are combined to the selected item

(4) Summary area: Combining results with waste percentage and total material costs. The material cost represents the pricing of the materials in the pricing database that was used in the combining run.

Tip: You can save the combining run to view it later and compare it with another combining run. To do so, click Save Combining Run at the bottom of the Combining Run Results dialog. No cut lists are generated when you save the combining run.

To view the results, open the Select Combining Run dialog by clicking the Combining/Estimating/Production Control ribbon tab and selecting Combine.

To save the combining run, click either of the following:

The material items that were combined to the existing inventory items are removed from the requisition and disappear from the Requisition # dialog box. The items that were combined to the supplier materials remain in the requisition until you send the items to a purchase order.