Manage changes to a production control job
You can view and assess the impact of changes caused by importing new or revised drawings or bills of materials into Tekla PowerFab.
Before the actual import, you can view a summary of changes and decide to accept the changes, reject them, or save them for later.
When the changes are saved for later, they are put on hold so that another person can review them and decide on the appropriate action. When a drawing is on hold, it cannot be worked on until the change has been reviewed and processed.
Import changes to a production control job
View the summary of revisions
When you are importing files, and revisions are found, the Change Summary dialog box opens.
- Object Type: Assembly (default), Drawing, All
- Change Type: Update (default), Addition, All
If there are no assembly updates in the job, you can see all changes to all items.
(2) View: An alternative way of selecting the Object Type (default Assemblies) and Change Type (default Updates)
(3) Grid: The list of changes
- Colors:
- Red: Update not possible
- Yellow: Highlights impacts if import performed
- Type: Change type
- Drawing #: Drawing number
- Main Mark: If the line represents a drawing, this cell is blank. Then the approval status is shown. IH stands for "Import Hold".
- Buttons:
- Linked: Yes appears if the material in the assembly in the production control job is linked to a requisition, purchase orders or inventory, or a cut list.
- Tracking: Yes appears if anything in the assembly has piece-tracking entries.
- TFS: Yes appears if anything in the assembly has been taken from stock.
- Shipped: Yes appears if anything from the assembly is on a load.
- Hold: When selected, puts the selected item on hold and sets the Approval Status to IH (Import Hold).
-
Action: Allows you to select the desired action for the selected row
- Allow implements the changes once
the import is completed. You can select Allow
only if the changes can be made. The changes are applied to the
Production Control bill of materials and the associated assembly drawings are
updated in the drawing log.
For changes that cannot be made, you can only select Save for Later or Prevent.
- Save for Later saves the changes and puts the selected items on hold so that they can be reviewed.
- Prevent rejects the changes.
Tip: To customize the grid, right-click it, and select Customize grid. - Allow implements the changes once
the import is completed. You can select Allow
only if the changes can be made. The changes are applied to the
Production Control bill of materials and the associated assembly drawings are
updated in the drawing log.
(4) Quick edit items: Allow you to select and apply actions for multiple rows at once.
- Set Selected on Hold: Allows you to place the selected items on hold.
- Set Selected Action: Allows you to select Allow, Save for Later or Save for Later in the Action column for the selected items.
(5) Summary of changes
(6) Details regarding the changes.
Manage changes
When you are importing revised drawings or bills of materials, you can review the changes and select the subsequent actions in the Change Summary dialog box.
View change report
If you select View Report, the report opens in Tekla PowerFab Report Viewer when you click Continue.
When you complete the import of changes by clicking Continue, a report on the changes is automatically saved to the Document Index.
You can change the view in the report by clicking the hyperlinks.
Review and manage saved changes in a job
To get an overview of which jobs have pending changes, you can customize the grid in Select Production Control Job to include the Has Pending Changes column. See Customize the layout of a dialog box.