Manage the project schedule

Tekla PowerFab
Modifierad: 26 mar 2024
2024i
Tekla PowerFab Tekla PowerFab GO

Manage the project schedule

You can create, view, and modify the project schedule of the current project in the Project Schedule dialog box.

To access the Project Schedule dialog box, do one the following:

To

Do this

Access the project schedule from the Project Management module At the bottom of the Project Management dialog box, click Project Schedule.

The Select Project dialog box opens. You can select multiple projects to provide a high-level view of the schedule status of these projects.

Access the project schedule from the Production Control module
  1. In the Production Control dialog box, click the Production Control ribbon tab.
  2. On the menu, select Project Schedule.
Note: You can access the Project Schedule dialog box from a production control job only if you have linked the production control job to a project management job.

The Project Schedule dialog box opens. The Schedule Tasks dialog box opens at the same time as well.

The Project Schedule dialog box contains multiple tabs:

  • Baseline Plan: Set and modify the current project baseline
  • Schedule Tasks: Add, modify, move, and delete tasks that are on the project schedule
  • Project Breakdown: Divide a project into sub-tasks. Usually done by sequence or lot number, but it can also be done by category, sub-category, or pay category.
  • Gantt Chart: View and modify the dates and completion percentages of different tasks