View and adjust the project schedule
In the Project Schedule dialog box, you can create, view, and modify the project schedule of the current project. Note that you can only access the Project Schedule dialog box from a production control job if you have linked the production control job to a project management job.
To access the Project Schedule dialog box, do one the following:
To |
Do this |
---|---|
Access the project schedule from the Project Management module |
|
Access the project schedule from the Production Control module |
|
The Project Schedule dialog box opens. The same dialog box is available in the Project Management module. Note that the Schedule Tasks dialog box opens at the same time as well.
-
On the Baseline Plan tab, you can set and modify the current project baseline.
-
On the Schedule Tasks tab, you can add, modify, move, and delete tasks that are on the project schedule.
-
On the Project Breakdown tab, you can divide a project into sub-tasks. Usually, this is done by sequence or lot number, but it can also be done by category, sub-category, or pay category.
-
On the Gantt Chart tab, you can view and modify the dates and completion percentages of different tasks.