Unlink materials between Production Control and Purchasing
Use the Un-Link Job command to unlink materials between Production Control and Purchasing when you need to manually manage the materials.
- In the Select Production Control Job dialog box, open a job and click the Production Control ribbon tab.
- On the menu, select .
- To only unlink specific types of materials, in the Un-Link Filters dialog box, select a filter type in the Type list, and click Select.
-
Do one of the following depending on the
filter type:
- Click the arrow buttons to move the items whose heat documents you want to view to the Included list.
- Type the maximum and minimum values for the items whose heat documents you want to view.
- Click OK.
- Click Un-Link.
- In the Un-Link Items dialog box, review the un-linking results.
- Click OK to close the dialog box.