Manage global production codes

Tekla PowerFab
Zmodyfikowany: 6 wrz 2024
2024i
Tekla PowerFab Tekla PowerFab GO

Manage global production codes

You can create, modify, and delete global production codes that are available in all production control and estimating jobs

Production codes link items or groups of items in an estimating job to items or groups of items in a production control job. They are used to group together material with similar work and to apply labor averages from estimating to the production control bill of materials.

Production codes exist on several levels:

  • Global: Production codes that can be used in all jobs in both Production Control and Estimating
  • Estimate-Specific: Production codes that can only be used within a specific estimating job and the linked production control job.
  • Production Control-Specific: Production codes only for the production control job

Production codes can be as broad or as specific as you like. For example, you can use one production code for the entire estimating job to add the labor estimates to the production control job. The hours will then be calculated based on all the work that must be done for the entire job. However, you can also set every piece mark to have its own production code, so that hours in the estimating job and in the production control job match for each item.

Tekla PowerFab calculates the labor times based on the production code. This means that using production codes allows you to plan production more accurately.

Note: In the Global Production Code Maintenance dialog, you can adjust only production codes, not labor times. Tekla PowerFab automatically calculates the labor times for the items that have been assigned a production code.

See also the following information:

Access Global Production Code Maintenance dialog

  1. Click the Maintenance ribbon tab.
  2. On the menu, selectProduction Control > Global Production Code Maintenance.

    The Global Production Code Maintenance dialog opens.

    Production Code: An abbreviation for the production code

    Description: A description for the production code. For example, you can use B1 for beams or C1 for columns.

    Override Hours: Select if you want to use aggregate units for the planned hours instead of the original estimated hours. Then type the hours in the field.

    However, if the manual override is used, the labor information does not include labor group percentages. Therefore, the labor group percentages cannot be applied to any production control stations.

    Further, the information cannot be applied to tasks in the project schedule and to resources that feed information to the production schedule.

    Manually overriding hours can also prevent you from comparing the linked production control job with the estimating job.

    An override applied in a production control job does not affect the estimate nor global information. The estimated hours are always created in the estimate. They are not overwritten by the production code properties.

    Aggregate Units: Select the suitable units in the drop-down menu.

    The hours associated with the production codes are only used in Production Control. Production codes do not affect or apply labor to estimating items.

    The purpose of the hours is to pull labor information from the estimate in the form of hours per ton and labor percentages by labor group.

Create a production code

  1. At the bottom of the dialog, click New.
  2. Name the production code and type a description.
  3. Do any of the following:

    To

    Do this

    Use the estimated labor times of items within the production code in Production Control

    The hours associated with the production codes are only used in Production Control. Production codes do not affect or apply labor to estimating items.

    The purpose of the hours is to pull labor information from the estimate in the form of hours per ton and labor percentages by labor group.

    • In the Aggregate Units list, select a calculation option.
    Override the estimated labor time of items within the production code in Production Control

    Manually overriding hours applies an aggregate unit, hours per ton, that can be applied to production control items.

    However, if the manual override is used, the labor information does not include labor group percentages. Therefore, the labor group percentages cannot be applied to any production control stations.

    Further, the information cannot be applied to tasks in the project schedule and to resources that feed information to the production schedule.

    Manually overriding hours can also prevent you from comparing the linked production control job with the estimating job.

    1. Select the Override Hours checkbox.
    2. Type the labor time in the field on the right side of the checkbox.

      To change the units, right-click in the field and select a suitable option in the context menu.

  4. Click Add.

The new production code is added.

Modify a production code

  1. Select the production code that you want to modify.
  2. Modify the properties.
  3. To update the production code properties, click Save.

Delete a production code

  1. Select the production code that you want to delete.
  2. Click Delete.
  3. In the confirmation dialog, click Yes to permanently delete the production code.