Modify the Gantt chart
The chart on the Gantt Chart tab of the Project Schedule dialog box gives you a visual representation of the schedule. You can modify the view of the Gantt chart according to your needs by including and excluding items, and scaling the chart. You can also move the tasks in the Gantt chart to move them earlier or later in the project schedule.
-
In the Project Schedule dialog box, click the Gantt Chart tab to open it.
-
To enable modifying the information, click Enter Edit Mode in the lower-left corner, or press Ctrl+E on the keyboard.
-
The left side of the tab shows the properties of schedule tasks.
-
The right side of the tab shows the schedule tasks visually as bars on the time line.
The tasks look different and behave differently depending on their task type:
-
Summary tasks (or main tasks) are displayed as orange bars. A summary task cannot be re-sized directly. Instead, you can re-size and move the sub-tasks to change the duration or dates of the summary task. When a summary task is moved earlier or later, the sub-tasks are moved by the same number of days.
-
Start/End tasks are displayed as blue bars. Start/End tasks can be re-sized and moved in the Gantt chart.
-
Milestone tasks are displayed as blue diamonds. Milestones can be moved in the Gantt chart, but they cannot be re-sized.
-
-
Links between tasks are represented by arrows from the predecessor tasks to the successor tasks.
-
Any cells that are highlighted with yellow can be modified.
-
Goto Task zooms to the beginning of the bar of the selected task.
-
Time Tracking Summary opens the Time Tracking Summary dialog box. For more information, see Add, modify, and view time tracking information.
-
Time Tracking Detail opens the Time Tracking Detail dialog box. For more information, see Add, modify, and view time tracking information.
-
Time Tracking Input opens the New Time Tracking Record dialog box. For more information, see Add, modify, and view time tracking information.
-
Production Schedule allows you to view the production schedule. For more information, see View the production schedule.
-
Date Filter allows you to select a date range that you want to see in the Gantt chart. When you apply the filter, tasks that are at least partially within the entered date range will be visible.
-
Scale chart to options: scale the Gantt chart to day, week, or month, according to your needs.
-
Show Links/Hide Links shows or hides the links between tasks.
-
Show Overview/Hide Overview shows or hides the overview section above the Gantt chart.
-
Expand All expands all summary tasks so that all sub-tasks are visible.
-
Expand Summary expands the task hierarchy so that all summary tasks are visible. Sub-tasks are not displayed.
-
Expand Level expands the selected task and other tasks with the same main task.
-
Collapse All collapses all summary tasks.
-
Save Image allows you to save the Gantt chart as a single image file.
Modify the dates of tasks
Modify the duration of tasks
Modify task properties
On the left side of the Gantt chart, you can modify the task properties, such as the duration, completion percentage, or used resource.
Note that only cells that are highlighted with yellow can be modified.
- On the left side of the dialog box, click a cell of the task.
- Modify the value in the cell according to your needs.
- Click Save to update the project schedule.
Modify display settings
Print a Gantt chart report
You can create and print a report that is an exact copy of the Gantt chart. Note that all content that you have selected in the Gantt Chart Display Settings section will be visible in the report as well.
- In the lower-right corner of the Gantt Chart tab, click Report.
- In the Print Review dialog box, click Setup... and adjust the paper size, orientation, margins, and printer properties according to your needs.
- Click Print.
- When the report has been printed, click Close to close the Print Review dialog box.