Update the project schedule
When you update a project schedule, Tekla EPM collects all time and progress status information on the current project in Production Control, Project Management, and Purchasing. Once the update process is ready, all activity is updated to the chart on the Gantt Chart tab. For example, if drawings have been submitted and approved, the percentage completed for drawing submittal will be updated.
You can see the last time the project schedule was updated in the upper-right corner of the Project Schedule dialog box, after Last Status Update.