Define and modify job-specific galvanizing settings

Tekla PowerFab
2022
Tekla PowerFab Tekla PowerFab GO

Define and modify job-specific galvanizing settings

In the Galvanizing dialog box, you can modify the pricing, minimum costs and freight information that is applied to a galvanized item in a specific estimating job. If you do not want to modify these settings for a single estimating job, Tekla EPM will automatically use the galvanizing settings that you defined in Estimating Company Standards.

  1. In the Select Estimating Job dialog box, do one of the following:
    • To define or modify galvanizing settings of a new estimating job, click New.
    • To define or modify galvanizing settings of an existing estimating job, select the job in the list, and click Edit.
  2. At the bottom of the Estimate Job Edit dialog box, click the Galvanizing button.
  3. In the Galvanizing dialog box, modify the galvanizing costs, the trailer capacity, the labor prep costs per pound, and the weight percent added.
  4. Click OK to save the changes.
  5. Click Save in the Estimate Job Edit dialog box.

The changes that you made to galvanizing settings are saved for the selected estimating job.