Manage contract information

Tekla PowerFab
変更済み: 20 8月 2024
2024i
Tekla PowerFab Tekla PowerFab GO

Manage contract information

You can add new contract items to either the original contract or a change order in the Contract Items dialog box. Contract items represent parts of the contract, such as detailing or materials. You can also modify, move, or delete existing contract items. Furthermore, you can define and adjust the properties of the project contract.

To access the Contract Items dialog box, do the following:

In the Contract & Invoicing dialog box, click Contract.

Original Contract: The sum of the original contract items

Change Order Net: the sum of the change order contract items

Total Contract: Original contract + change order net

Approved Change Orders Not In Contract: The number of approved change orders not assigned to a contract item

The Contract Items dialog box opens.

Add a contract item to the original contract

  1. On the Contract Items tab of the Contract Items dialog box, click New Contract Item.

    The Contract Item dialog box opens.

  2. Define the properties.
    Option Description
    Description Type a description for the contract item.

    The description is used in project management reports.

    Type Select Original Contract in the drop-down list.
    Amount Type the costs of the contract item.
    Override Retainage Select if you want to modify the default values in Completed Work and Stored Materials.

    You can set a different value for each line item.

    Schedule Task Select the project schedule task that you want to link to the new contract item.

    When you link a contract item to a schedule task, Tekla PowerFab automatically finds the completion percentage of the contract item from the project schedule.

    This allows you to automatically calculate the amount to be invoiced based on the completion percentage.

    Notes Type any additional notes.
  3. Click Save.

The new contract item is added to the list on the left-hand pane.

The Contract & Invoicing dialog box now shows the totals for the contract and the sum to be invoiced.

You can now create invoices for the contract item. For more information, see Manage invoices.

All invoices related to the contract item are displayed in the Invoices section, below the contract item properties.

Add a contract item as a change order

Create a contract item for changes orders. You can link an approved change order to your schedule of values as part of a contract item so the data will automatically feed into your contract and invoice.

  1. On the Contract Items tab of the Contract Items dialog box, click New Contract Item.

    The Contract Item dialog opens.

    Description: Type a description for the contract item.

    The description is used in project management reports.

    Type: Select Change Order.

    Schedule Task: Select the project schedule task that you want to link to the new contract item.

    When you link a contract item to a schedule task, Tekla PowerFab automatically finds the completion percentage of the contract item from the project schedule. This allows you to automatically calculate the amount to be invoiced based on the completion percentage.

    Notes: Type any additional notes about the contract item.

  2. Click Save.

    The new contract item is added to the list on the left-hand pane.

  3. To define the costs of the contract item, go back to the Project Management dialog box, and click Change Orders.

    The Change Order dialog opens.

  4. Select the change order that you want to link to the contract item.

    Ensure that Approved is selected.

  5. In Contract Item, select the new contract item.
  6. To save the changes, click Save.

When you return to the Contract Item dialog box, you can see that the costs of the selected change order are now used in the Amount field for the contract item. The selected change order is displayed in the Change Orders section, below the contract item properties.

The net amount of the change order will also be visible in the Contract & Invoicing dialog box.

Modify a contract item

  1. On the left-hand pane of the Contract Item dialog box, select the contract item that you want to modify.
  2. Modify the description, type, amount, schedule task, and notes.
  3. Click Save to update the contract item properties.

Move a contract item up or down

  1. On the left-hand pane of the Contract Item dialog box, select the contract item that you want to move.
  2. Click the Move Up and Move Down buttons to move the item to the desired position.

Delete a contract item

Deleting a contract item is permanent and cannot be undone.

Note: The contract items that have been invoiced cannot be deleted.
  1. On the left-hand pane of the Contract Item dialog box, select the contract item that you want to delete.
  2. Click Delete.
  3. To permanently delete the contract item, click Yes in the confirmation dialog box.

Adjust the contract properties

  1. In the Contract Items dialog box, click the Other tab to open it.
  2. Adjust the contract properties:

    Option

    Description

    Contract #

    The contract number.

    The contract number is displayed in the standard AIA G702 invoice form.

    Type the contract number in the Contract # field.

    Contract For

    A brief description of the contract, displayed in the standard AIA G702 invoice form.

    Type a description in the Contract For field.

    Retainage - Completed Work

    The percentage of the invoiced completed work amount that is retained until the end of the project. The default value is 10%.

    Type a value in the Retainage - Completed Work field.

    Stored Materials

    The percentage of the invoiced stored materials amount that is retained until the end of the project. The default value is 10%.

    Type a value in the Stored Materials field.

    Notes

    Any additional notes or information about the contract.

  3. Click Save.

    A message appears, telling you that the information has been saved.

  4. Click OK to close the message.
役に立ちましたか?
前へ
次へ