View and adjust the project schedule
You can create, view, and modify the project schedule of the current project in the Project Schedule dialog box.
To access the Project Schedule dialog box, do one the following:
To |
Do this |
---|---|
Access the project schedule from the Project Management module | At the bottom of the Project Management dialog box, click Project Schedule. |
Access the project schedule from the Production Control module |
|
Note: You can access the Project
Schedule dialog box from a production control job only if you have linked the production
control job to a project management job.
The Project Schedule dialog box opens. The Schedule Tasks dialog box opens at the same time as well.
The Project Schedule dialog box contains multiple tabs:
- Baseline Plan: Set and modify the current project baseline
- Schedule Tasks: Add, modify, move, and delete tasks that are on the project schedule
- Project Breakdown: Divide a project into sub-tasks. Usually done by sequence or lot number, but it can also be done by category, sub-category, or pay category.
- Gantt Chart: View and modify the dates and completion percentages of different tasks