Complete work packages
Once all assemblies in the work package are considered complete, the Work Package Status is automatically updated to Completed: Yes. You can also complete one or more work packages manually.
Assemblies within the work package that have a route assigned to them are deemed complete once they have a production tracking record for the Dashboard Productivity Station station that is nominated for the assigned route. See Manage routes.
The following cases are exluded from this logic:
- Assemblies that have a route assigned but the Production Productivity station nominated for the assigned route is set to [None]
- Assemblies within the work package that do not have a route assigned
Once all the assemblies in the work package are considered complete, Work Package Statusis automatically updated to Completed: Yes.
Once assemblies and parts in the work package have passed through fabrication, production managers managers can also manually complete one or more work packages at a time. This may be used when production tracking is not being applied.
Complete work packages manually
If you want to remove the completion, select Uncomplete Selected Work Packages (Manually)/Remove manual completion on the Work Packages/Work Package ribbon tab.