2. Setup in Steel Projects PLM

Tekla PowerFab
Not version-specific
Tekla PowerFab Tekla PowerFab GO

For an overview, see Steel Projects PLM Integration.

1. On the Fabrication Job data tab, click Import.

Image
2-1.png

2. Next to Link, enter a work order name and click New.
 
Image
2-2.png

3. From the Type drop-down, select FabSuite - Nest request import.
 
Image
2-3.png


4. Select the directory where Tekla PowerFab exports the nest request.
 
Image
2-4.png

5. Click Save, then Quit.

6. Click Import again.
 
Image
2-1.png

7. For Link, enter a name for the cut list import, then click New.
 
Image
2-7.png

8. For Type select FabSuite -  Plugin - Cut list, then click Options.
 
Image
2-8.png


9. Open your Tekla PowerFab Remote Monitor and click Settings

You need the IP Address and Socket Port for the next step.
 

Image
2-9.png


10. Back in PLM, in the Options dialog box, enter "tcp://" then the IP address followed by a colon ":"  and then the port found in the previous step.  Enter your remote user login and password from Tekla PowerFab.

11. Click Check to verify the connection.
 

Image
2-10.png


12. Select the Jobs and pces tab. Check Show only valid cut lists and Show only shared cut lists.

The other settings are optional depending on your workflow.

Image
2-11.png


13. Click OK, then Save and Quit.

14. Go to the Nesting data tab, then click Stock Import.

Image
2-12.png

 

15. For Link, add the stock import and click New.
 

Image
2-13.png

16. For Type select FabSuite - Plugin - Inventory, then click Options.
 
Image
2-14.png


17. Enter the same URL, Login, and Password as in the step above, then click Check to verify the connection.

Options on the Parameter tab depend on your workflow.

Check with Steel Projects support if you have any questions.

18. Click OK when done.

Image
2-15.png


19. Click Save and Quit.

20. Select the Feedback data tab and click Export.

Image
2-16.png

 

21. For Link, enter a name for the feedback export and click New.

Image
2-17.png


22. For Type, select FabSuite - Plugin - 4D, and select an export directory.

23. Click Options.
 

Image
2-18.png


24. On the Options Connection tab, enter the same URL, remote user, and password as in the previous steps.

25. Click OK.
 

Image
2-19.png


26. Save and Quit.

 

For the next steps, see Steel Projects PLM Integration.