Example: Use control numbers to indicate the erection order
This example shows how to assign control numbers to six concrete walls. As four of these walls have the same cast unit position, you cannot make a clear distinction between the cast units based on their position number. That is why each wall will get a unique identifier that indicates their erection order at the site. The erection order also affects the order of shipping. For example, the wall number 1 needs to be shipped on top of the delivery, because it will be erected first on the site; the wall number 2 should be the second on the bundle, because it will be erected next; and so on.
The following image represents the desired end result.
|
Erected as 1st |
|
Erected as 2nd |
|
Erected as 3rd |
|
Erected as 4th |
|
Erected as 5th |
|
Erected as 6th |
To assign control numbers to the concrete walls: