Project status visualization
Use the Project Status Visualization tool to review the status of model objects in a specific time frame.
For example, you can use Project Status Visualization to display the erection schedule for groups of parts using different colors, and to identify the parts that are scheduled to be fabricated during a specific time period.
Before you can create project status visualizations, you need to define some color and transparency settings that include object groups based on date rules.
You can also define tasks for parts and assemblies using Task manager. The project status visualization can then be based on tasks.
Create a visualization
Create visualization settings to view the project status of model objects in a specific time frame.
- On the Manage tab, click Project status to open the Project Status Visualization dialog box.
-
Modify the visualization settings.
- In the Object representation list, select one of the predefined object representation settings.
- Define a start and end date for the time scale slider.
- Define the length of the time step.
- Select the Refresh view automatically check box.
- Enter a unique name in the box next to the Save as button.
- Click Save as to save the visualization settings.
- To view the visualization in the model, click the step buttons.
Copy visualization settings to another model
You can copy project status visualization settings to another model. The visualization settings files are located in the model's \attributes folder, and they have the file name extension .4d.
Delete visualization settings
Delete the project status visualization settings that have been created using the Project Status Visualization tool.
Project status visualization example: Visualize the erection schedule of a project
This example shows how to visualize erection schedules using the Project Status Visualization tool.
-
Define an erection schedule for parts using the
Planned start user-defined attribute.
-
Select objects for the visualization by creating an object group that defines which objects are shown in the model during the visualization.
-
Define the color and transparency of the selected objects using color and transparency settings that define
how the objects are shown during the visualization.
-
Define a time period for the visualization.
-
View the erection schedule using the
Project Status Visualization tool.