Summary

When working to the 2019 version of the code the punching checks to ACI 318 checks are amended as follows:

  • ACI 318-19 Section 22.6.4.3, Figure R22.6.4.3 - Modification of critical perimeters to take account of slab openings - Limit change from 10 h to 4h.

  • Clause 22.6.5.2 - A new size modification factor λs has been considered in concrete shear strength calculation.