Fixes

Apply
Defect number Development area Description
EPM-8883 Estimating

In the Select Estimating Job dialog, you can now add the Total Cost field.

EPM-10112 Production control

The Percent Shipping Complete field has been added to the WorkPackages dialog. It is available on the WorkPackages display area and the WorkPackage object returned from an API request.

EPM-10137 Production control

Previously, material could not be swapped between jobs unless it was the same length. This has been relaxed and liner material can be swapped between jobs so long as material is not taken from the other job.

EPM-10139 Production control

The import warnings text has been updated to reflect that an item may be sequenced or included on a work package

EPM-10308 Production control

When a navigation tree has the Dimensions field expanded and the metric/imperial mode is selected, the displayed options are not updated to the equivalent dimensions. This issue has now been fixed.

EPM-9825 Production control

Previously, in Production Control, when exporting a work package to a .pfxt file and including drawing files, drawings with multiple revisions may not have been correctly associated with their respective revisions upon import. This issue has now been fixed.

EPM-9867 Production control

Previously, in Production Control, when exporting a Work Package to a .pfxt file, excluding either Drawings or CNC Files from the export resulted in both being excluded. This issue has now been fixed.

EPM-10242 Administration

Tekla PowerFab now supports MySQL 8.4.

EPM-9031 Administration

In Administration, in the Remote Permissions dialog, all dependent checkboxes are cleared and disabled if the parent permission is unchecked.
Production Control/Project Management tab: 
- Production Control - Material: View TFS Details is enabled when View Details is selected.
- Production Status: With Insp Fail is  enabled when Add is selected
- Shipping Status: Load w/ Insp Fail is enabled when Load is selected.
Inventory/Inspection/Time Tracking tab: 
- Inspection: Add, Add Document, Update, and Delete are enabled when View is selected.
- Time Tracking: Add - Allow Early Start Date/Time and Add - Allow Late End Date/Time are enabled when either Add - Self or Add - All Employees is selected.

EPM-9256 Administration

A Filter dropdown menu and a Search bar have been added to the Address Book - Contacts dialog.

EPM-10186 Purchasing

Previously, when viewing a Stimulsoft report, the Email Excel option exported to a file with the .xls extension. The Email Excel option now exports to a file with the .xlsx extension. 

EPM-10188 Purchasing

The On-Order Sub-Total field for Purchase Orders now takes into account the subcontract items on the purchase order.

EPM-10054 Inventory

In Inventory Transaction History, the following reports have been redesigned in Stimulsoft Reports:
- TFS - Taken from Stock
- RTS - Returned to Stock
- Scrap - Added to History
- Waste - Added to History
 

EPM-10244 Requisitions

Employee information has been added to the Station Summary by Employee report data.

EPM-8767 Combining

Finish and Remarks are now available in the lower-left area of the Combining Run Results  dialog. They can be added by customizing the grid.

EPM-10132 Integrations

Previously, when publishing to the Trimble Connect Status Sharing service from very large projects, an error can occur. This issue has now been fixed.

EPM-10230 Integrations

Repeated sequence data returned through the API has been corrected, and an option to include or exclude Work Package info has been added.

EPM-10235 Integrations

A new field has been added to SigmaNest Settings, Inventory Transfer Settings tab. This new field stores the path to the directory in which remnants are stored when transferred to SimTrans.

EPM-10162 Tekla PowerFab Go

Previously, on the Production Planner, updating piece tracking data could cause the work package percent completed to show incorrectly.This issue has now been fixed. 

EPM-10239 Tekla PowerFab Go

In 2025i, not all parts were drawn in the nest image of a nest created by PowerFab when it was viewed from the cut list or from PowerFab Go. This issue has now been fixed.

EPM-7171 Tekla PowerFab Go

In Tekla PowerFab Go, Camber has been added to show in the Cut List view.

EPM-7950 Tekla PowerFab Go

In Tekla PowerFab Go, you can now add the Comment field to the part and pick list views in Cut Lists.