Manage schedule templates
You can create, modify, and delete templates that are used as the basis of project schedules with predetermined tasks and settings.
Creating schedule templates saves time when creating project schedules, because you can easily apply the template to any project schedule. When the template is applied to the project schedule, you can modify the tasks according to your needs.
Create a schedule template
-
Go to Maintenance > Project
Management > Schedule Templates.
The Schedule Templates dialog opens.

- Click New Template.
- In the Template Description field, type a name for the new template.
-
Click Add
Template.
The template is added to the list on the left side of the dialog.
-
To add tasks to the
template, do the following:
-
Click New
Task.
The Schedule Template Task dialog opens.

- Type a description for the task.
-
Modify the properties.
Option
Description
Parent Task If the task you are creating is a subtask, for an existing task, you need to select the main task.
Select a task in the list. If you are creating a top-level task, select None.
Note: You cannot modify the task type, duration, or original estimate time of a main task if you add a subtask.
Task Type Specifies the behavior of the task on the Gantt Chart tab. The available task types are:- Start/End: An action to be performed over a period of
time. Properties include the start date, end date,
and duration. Appears as a blue bar on the Gantt
chart.
Start/End tasks can be directly resized an moved on the Gantt Chart tab.
-
Summary: Reflects the duration of all its associated sub-tasks and appears as an orange bar on the Gantt chart.
The start date of a summary task is automatically set to the earliest date of the subtasks. The end date is set to the latest subtask end date, and the percent completed is aggregated based on the status summary method.
Summary tasks cannot be resized on the Gantt Chart tab directly. However, the subtasks can be resized and moved, and the summary main task will resized and moved accordingly.
- Milestone: An event in the schedule. For example, a project kickoff meeting can be a milestone task. The end date and the start date are always the same, and the duration is set to one day. Appears as a blue diamond on the Gantt chart.
Apply Breakdown Links When selected, the links set in the project schedule are added between subtasks. For example, any links set between sequences 1, 2, and 3 would be added.
When cleared, the links set between subtasks are not added, even if they have been set in the project schedule.
Duration The expected number of working days to complete a task.
The duration can only be adjusted if the task type is set to Start/End.
Type the number of days in the Duration field.
Original Estimate The time originally estimated for the entire main task or a subtask. The hours will automatically be distributed among the subtasks on the Gantt chart.
Type the time in hours in the field.
Status Link The information that affects the status of the task when the project schedule is updated. The available options are:
- Drawings Approved: The number of drawings with the Approved status
- Material Purchased: The production material that is linked to material that is either in stock or on order
- Material Received: The production material that is linked to material that is in stock
- TFS: The production material that has been cut
- Production Completed: The production material that has been assigned a route and has completed all stations in that route
- Production Progress: The production material that has been assigned a route and has completed some stations in that route
- Station Progress: The production material that has been assigned a route that includes the selected station and has completed that station
- Shipping Destination Progress: The production material that has been assigned a shipping route that includes the selected destination and has completed that destination
- Shipping Completed: The production material that has completed all assigned shipping destinations
Select an option in the list.
Status Summary Method The method that determines how the percentage completed of a main task will be calculated from the subtasks. Each option specifies the weight that is given to each subtask in the calculation. The available options are:
- No Factor: No weight is given to the individual subtasks. The percentage completed of the main task is an average of the subtasks.
- By Quantity: The percentage completed is weighed by the quantity of each subtask
- By Weight: The percentage completed is weighed by the weight of each subtask
-
By Duration: The percentage completed is weighed by the duration of each subtask
Select a calculation method in the list.
Resource An object with a time-based capacity to be added on a production schedule, and the resource by which station work will be executed.
Linking a task from the project schedule to a resource connects the project and production schedules.
Select a resource in the list.
- Start/End: An action to be performed over a period of
time. Properties include the start date, end date,
and duration. Appears as a blue bar on the Gantt
chart.
-
Click New
Task.
- Click Add.
- In the Schedule Templates dialog, click Save Template.
Create links between tasks
You can define dependencies between two tasks. By creating links, you can make the schedule cascade from one task to another. You can modify and delete existing links.
- A task cannot link to itself.
- A link cannot be created between a task and one of its subtasks.
- Duplicate links are not allowed. There can be only one link between a pair of tasks.
- Link cycles are not allowed. For example, if a link is created from task 1 to task 2, a link cannot be created from task 2 to task 1.
- When you use links, and the duration of an item changes, the positions of all linked items also changes. Do not link items that need to remain static, or are independent from other items in the schedule.
- Select the new task in the navigation tree.
-
Do any of the following.
To
Do this
Add a link that ends with the current given task Note: If a previous snapshot is displayed instead of the current project schedule information, you cannot add a predecessor link.
- Click New Predecessor Link.
- In Link From, select the starting task of the link.
- In the upper (From) Position field, select if the link originates from the start or end of the starting task.
- Link To, select the task where the link ends.
- In the lower (To) Position field, select if the link ends at the start or finish of the second task.
-
In Minimum Interval, type the minimum number of working days between the two tasks.
The minimum interval is enforced in the Gantt chart. The later task cannot be moved earlier in the Gantt chart than the value in the Minimum Interval field determines.
- Click Add.
For example, to define that shipping must start when the fabrication is finished, select Shipping and set the link a follows:- Link From: Fabrication
- Upper Position: Finish
- Lower Position: Start
- Minimum Interval: 0 days
Add a link that begins with the current task Note: If a previous snapshot is displayed instead of the current project schedule information, you cannot add a successor link.
- Click New Successor Link.
- In the upper Position field, select if the link originates from the start or end of the starting task.
- In Link To, select the task that is the ending point of the link.
- In the lower Position field, select if the link ends at the start or finish of the second task.
- In Minimum
Interval, type the minimum number of working days between
the two tasks.
The minimum interval is enforced in the Gantt chart. The later task cannot be moved earlier in the Gantt chart than the value in the Minimum Interval field determines.
- Click Add.
For example, to define that shipping must start when the fabrication is finished, select Fabrication and set the link a follows:- Upper Position: Finish
- Link To: Shipping
- Lower Position: Start
- Minimum Interval: 0 days
View and modify link properties - Click Link Properties.
- Modify the starting task, ending task, the task positions, and interval according to your needs.
- Click Save to update the link properties.
Delete a link - Click a link in the list to select it.
- Click Delete Link.
- In the confirmation dialog, click Yes to permanently delete the links.
- To save the links, click Save.
Modify a schedule template
- In the list on the left of the Schedule Templates dialog, select the template that you want to modify.
-
Do any of the following:
To
Do this
Add a task to the schedule template See Create a schedule template. Modify an existing task - In the Template Tasks list, select the task that you want to modify.
- Click Properties.
-
In the Schedule Template Task, modify the task description, properties, and links.
For more information on task properties and links, see Create a schedule template and Create links between tasks.
- Click Save to save the changes.
Move a task earlier or later in the schedule template - In the Template Tasks list, select the task that you want to move earlier or later in the schedule template.
- Click the Move Up and Move Down to change the location of the task.
Delete a task from the schedule template Note: Deleting a task from the schedule template is permanent and cannot be undone.
- In the Template Tasks list, select the task that you want to delete.
- Click Delete Task.
- To permanently delete the task, click Yes in the confirmation dialog.
- Click Save Template to save the changes.
Delete a schedule template
Note that deleting a schedule template is permanent and cannot be undone.
- In the list on the left of the Schedule Templates dialog, select the template that you want to delete.
- Click Delete Template.
- To permanently delete the schedule template, click Yes in the confirmation dialog.