Add subcontract items to a purchase order from a load

Modified: 18 Nov 2024 Tekla PowerFab 2025i Tekla PowerFab GO 2025i

Add subcontract items to a purchase order from a load

You can add subcontract line items to a purchase order automatically from a load. This makes creating subcontract orders, for example, for subfabrication, surface treatment, and freight much easier and removes the need for duplication.

  1. In the Loads dialog, select a load.
  2. Click Load Properties.

    The Load Properties dialog opens.

  3. Click Add to Purchase Order.

    The Select Purchase Order dialog opens.

  4. Select a purchase order and click OK.

    You can also create a new purchase order.

    The Add to Subcontract Purchase Order Options dialog opens.

  5. Define the properties.

    One Summary Line: When selected, adds a single line displayed on the purchase order that represents the entire load

    Description: Type any additional information. It will be populated on the purchase order line.

    One line for each assembly: When selected, imports a multiline entry on the purchase order that includes complete assembly information from the load

  6. Click OK.

    The subcontract items are included in the selected purchase order.

    For information on receiving subcontract items, see Receive subcontract items.