Schedule work packages
In the Production Planner tool in Tekla PowerFab Go, you can schedule work packages across workshops and departments. You can also reserve capacity for future work packages.
Schedule work packages for a workshop
To reschedule or unschedule a work package, tap the three dots to open the menu and select the appropriate option.
Department dependencies are validated based on department numbers. You get a warning if an earlier department is scheduled or rescheduled after a later one.
Schedule future work packages
In the workshop view, you can reserve capacity for upcoming projects so that you can identify gaps in the schedule and fill them.
You can define the required work loadings by both hours and weight required for each department within a future work package.
You can modify the future work package, if there are any changes in the project schedule or requirements.
Before you start creating a future work package, you must have a production control job. If you are working on a newly awarded project and have created a project management job, we recommend that you create the production control job at the same time to allow you to create your future work packages.
To reschedule or edit the details
or capacity of a future work package, tap the three dots
and select the desired
action.
When you add the production work package to the schedule, the system checks to see if there are any future work packages for the same job. See Deduct production work package capacity from future work packages.
Deduct production work package capacity from future work packages
When you add the actual production work package to the schedule in Tekla PowerFab Go, the system checks to see if there are any future work packages for the same job. You can then deduct the production work package hours and weight from existing future work package reservations, ensuring accurate capacity planning and preventing duplicate bookings.
You can deduct capacity from future work packages both in the workshop view and the department view.
The work package capacity is updated and the hours in the future work package have diminished.
When all the capacity in a future work package has been assigned, the future work package is deleted.
Schedule department work
The department planner in Tekla PowerFab Go Production Planner provides the ability to plan work packages at department level within the selected workshop, which provides a more granular planning experience.
Departments of the same work package can be scheduled to different weeks, the same department can be split over multiple weeks, and different departments can even be scheduled to different workshops.
The department planner displays one workshop at a time, with each department and work area appearing as its own column from left to right.

(1) The selected workshop
(2) Department
(3) Work area
(4) Work package
(5) Capacity



.
button either:
icon indicates that
the work package has been split over multiple weeks.