Fixes

Defect number Development area Description
EPM-9525 Estimating

Previously, stitch welds in IFC Files from Tekla Structures sometimes imported with a quantity set to the number of stitches and with a length of the full welded length. This resulted in inflated labor requirements. This issue has been fixed by setting the weld quantity to 1 if we use the full length rather than the stitch length.

EPM-9621 Project management

Previously, large jobs could take a long time to open and use a large amount of memory to open the Project Schedule. The overhead required has now been reduced to not load the drawing and Bill of Material information until it is required, making the Project Schedule open more quickly.

EPM-9298 Production control

When creating a cut list, if the new cut list has some items which match the filter and some that do not, you are prompted for what items to include. Previously, "Include only items matching the current filter" and "Don't save partially matched cutting details to the cut list" were acting the same. This issue has now been fixed.

EPM-9486 Production control

Previously, you might have got an error "Can't update table productioncontrolcutlists" when deleting multiple jobs. This issue has now been fixed.

EPM-9508 Production control

Previously, in the CNC Files dialog, the Hole Diameter field was blank. This issue has now been fixed.

EPM-9594 Production control

Previously, it was sometimes possible to get an access error when removing an inspector from an inspection filter. This issue has been corrected.

EPM-9606 Integrations

SaveNest API commands run without a CombinationRunID were failing when PLM sent in Sequence or Lot # in the Main Mark field. This restriction has been loosened, allowing parts that match on all fields except Main Mark to nest when the SaveNest originates from Steel Projects PLM.

EPM-8760 Shapes/grades/sizes

Shape/Grade/Sizes Reports can now be filtered for Shapes that are activated, have additional data available, and have been converted to Stimulsoft reports. 