A snapshot represent the baseline plan at
previous points in time. Each time you make a change to the project schedule, Tekla
PowerFab automatically takes a snapshot.
If you want to mark the snapshot as a particularly
important point in the schedule, you can record it as a savepoint.
You can use the snapshots to compare the project schedule at two different points in
time and view the impacts of changing the schedule. You can also load existing
snapshots to view the project schedule at a particular point in time.
-
In the Project
Schedule dialog box, on the Baseline
Plan tab, expand the Snapshots section by clicking the arrow on the left side of Snapshots.
You can see the currently
displayed snapshot after Currently Viewing Snapshot. If you are viewing the current project schedule, the value will be
[Current].
-
Do any of the following:
To
|
Do this
|
Load a snapshot |
-
In Schedule
Snapshot, select a snapshot in the list.
If you only want the list to display the
savepoints that have been recorded, select the
Only
Show Savepoints checkbox.
- Click Load
Snapshot.
The
Project
Schedule dialog box displays the project schedule at the
selected point in time.
To
view the current project schedule again, select
[Current] in the Schedule
Snapshot list.
|
Record a savepoint |
- In the Project
Schedule dialog box, make any changes.
- Click Record
Savepoint.
The Snapshot dialog box opens.
- Type a description for the savepoint.
- Ensure that the Is
Savepoint checkbox is selected.
-
Click
Save.
You are prompted to confirm entering edit
mode.
- Click Yes.
|