Manage global production codes
You can create, modify, and delete global production codes that are available in all production control and estimating jobs
Production codes link items or groups of items in an estimating job to items or groups of items in a production control job. They are used to group together material with similar work and to apply labor averages from estimating to the production control bill of materials.
Production codes exist on several levels:
- Global: Production codes that can be used in all jobs in both Production Control and Estimating
- Estimate-Specific: Production codes that can only be used within a specific estimating job and the linked production control job.
- Production Control-Specific: Production codes only for the production control job
Production codes can be as broad or as specific as you like. For example, you can use one production code for the entire estimating job to add the labor estimates to the production control job. The hours will then be calculated based on all the work that must be done for the entire job. However, you can also set every piece mark to have its own production code, so that hours in the estimating job and in the production control job match for each item.
Tekla PowerFab calculates the labor times based on the production code. This means that using production codes allows you to plan production more accurately.
See also the following information:
Access Global Production Code Maintenance dialog
Create a production code
The new production code is added.
Modify a production code
- Select the production code that you want to modify.
- Modify the properties.
- To update the production code properties, click Save.
Delete a production code
- Select the production code that you want to delete.
- Click Delete.
- In the confirmation dialog, click Yes to permanently delete the production code.