Create a new load
You can start creating a new load in the Loads dialog box.
- In a Production Control job dialog box, click the Production Control ribbon tab.
-
On the menu, click Load
Tracking.
The Loads dialog box opens.
-
Click New
Load.
The Load Properties dialog box opens.
-
Define the load
properties.
For details, see Load properties.
-
Click
Save.
The Load Properties - Not Shipped dialog box opens.
-
To add material to the load do
the following:
-
Click Add
Material.
The Loads - Add Material dialog box opens.
- Click the arrows to move the materials that you want to load to the Included list.
- Modify the properties.
- Click Add Material.
For details on adding materials to a load, see Add or preassign materials to a loadThe items and quantities that have been moved to the Included side are added to the selected load.
Load tracking settings for accessories are reflected in the shipping weight assigned to the load assembly.
-
Click Add
Material.