You can copy an existing job to use it as the base of a new similar job. Copying an existing job makes creating the new job quicker, as you do not have to set all properties manually or create items one by one.

  1. Go to Maintenance > <Module> > Job Maintenance.

    The Job Maintenance dialog box opens.

  2. Select the job that you want to copy.
  3. At the bottom of the dialog box, click Copy.
    The Enter Value dialog box opens.
  4. Type a number for the new job.
  5. Click OK.

Tekla PowerFab creates a new job based on the selected job. You can modify the properties of the new job by using the Edit functionality in the module.