Manage production codes used in a production control job
You can create new production codes for the production control job, or modify and delete existing production codes in the PDC Production Codes dialog box. You can override the estimated hours and use aggregate units to calculate the planned labor time on a job. This labor time can then be used in production schedules and project schedules.
To assign production codes to material items, use the Global Edit command. For more information, see Modify multiple production control items.
Open the PDC Production Codes dialog box
- In the Select Production Control Job dialog box, select a job and click the Production Control ribbon tab.
- On the menu, select .
The PDC Production Codes dialog box opens.
Create a production code
The new production code is added.
Modify a production code
Delete a production code