Use the Link
Job command to link materials in Production Control to pre-purchased advanced bill materials. Tekla EPM uses reference numbers to match the materials across modules. Any unlinked materials,
such as loose pieces, will be loaded into a requisition or a purchase order to be
purchased.
-
In the
Production Control dialog box, click the Production Control ribbon tab.
-
On the menu, select
.
-
To limit which materials are
linked, in the Link
Filters dialog box, select a filter type in the Type list, and click Select.
-
In the Filter dialog box, do one of the following depending on the filter
type:
-
Click the arrow buttons to move the items whose heat
documents you want to view to the Included list.
-
Type the maximum and minimum values for the items
whose heat documents you want to view.
-
Click
OK.
-
If necessary, select the
If updating a cut list item,
exclude from being cut check box.
By selecting the check box, you can ensure that Tekla EPM does not invalidate the entire cut list when an item in the cut list is
updated. Updated items will be saved in the inventory to be processed
later.
-
Click Link.
-
In the Link
Items dialog box, click if you want to load material information to a requisition
or a purchase order.
-
Click the desired requisition or purchase order.
-
Click
OK to load the materials.
-
Click
OK to close the Link
Items dialog box.