New way to control pour unit visibility in Organizer

Tekla Structures
2022
Tekla Structures

New way to control pour unit visibility in Organizer

In Tekla Structures 2022, you can now control in Organizer whether pour units or cast-in-place cast units are used as the highest cast-in-place hierarchy level in Organizer.

You can find the Pour units enabled setting in Organizer Settings, on the Synchronization tab:

  • Select the check box to use pour units as the highest cast-in-place hierarchy level.

  • Clear the check box to use cast-in-place cast units as the highest cast-in-place hierarchy level.

Organizer can show either pour unit or cast-in-place cast unit hierarchy at a time.

Previously, you could control the visibility of pour unit cast-in-place hierarchy in Organizer only by using the XS_ENABLE_POUR_MANAGEMENT advanced option. Now the advanced option value is used when you create a new model or open an existing model that was created with a previous Tekla Structures version. When you change the Pour units enabled setting in Organizer, this changed setting is now used regardless of the advanced option value.

Changing the Pour units enabled setting causes synchronization

When you select or clear the Pour units enabled setting, Organizer is fully synchronized when you close the Settings dialog box. Take this into account when changing the setting in large models, as synchronization may take some time.

Note that categories with manually added content lose the pour unit or cast-in-place cast unit content, depending on whether Pour units enabled is selected or not. If you change the setting again, Organizer does not add the manually added content back to the categories. You need to manually add the content again.

Bylo to užitečné?
Předchozí
Další